Comparing Baselines
Resolved · Low Priority · Version 2007
Caroline has attended:
Project Intro Intermediate course
Comparing Baselines
How am I able to compare my saved baselines in a Gantt chart view?
RE: Comparing Baselines
Hi Caroline
Thank you for your question. After opening your plan take a look at View > More Views and from the list select Multiple Baselines Gantt By default this view shows you Baseline, Baseline1 and Baseline2
If you would like to see other baselines go to Format > Bar Styles and swap out the baseline starts/finishes for the fields that you require.
I hope this helps - do let me know if you have any further questions.
Kind regards,
Andrew
RE: Comparing Baselines
That only shows me a comparison of each sub-heading, not individual tasks. Is it possible to see a comparison of individual tasks?
Caroline
RE: Comparing Baselines
Hi Caroline
Thank you for cominig back to me. Multiple baselines gantt view shows the baselines for summary tasks and individual tasks.
Check to see that the sub tasks are fully displayed by clicking on the show button and selecting All Subtasks.
If you would rather not have the summary tasks displayed go to Tools > Options > View and de-select Show summary tasks.
Let me know how you get on.
Kind regards,
Andrew
RE: Comparing Baselines
It is still only showing the baseline comparisons for the summary tasks and not the individual tasks as required... any ideas?
RE: Comparing Baselines
Hi Caroline
Take a look at the Tracking Gantt view (View > Tracking Gantt). Do you have the same problem in this view too or does each task have a baseline? In this view the live plan is show in blue and/or red. The baseline is drawn below the live plan in grey.
Kind regards,
Andrew
RE: Comparing Baselines
No - that view only shows the baseline below the summary tasks and not individual tasks also...
Does it make a difference that I am trying to do this in a 'Master Project' with about 4 or 5 individual projects pulled through?
Caroline
RE: Comparing Baselines
Hi Caroline,
Yes that does make a difference.
Set the baseline on each individual projects to see them displayed in the combined view.
Kind regards
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |