levelling resources across proje

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Levelling resources across projects in Project | MS-Project forum

Levelling resources across projects in Project | MS-Project forum

resolvedResolved · Medium Priority · Version 2003

Sabine has attended:
Project Intro Intermediate course

Levelling resources across projects in Project

How / on what basis does Project choose to level resources across several individual projects when the resources are from a shared resource pool (and projects are individual projects, not part of a master project)?

RE: Levelling resources across projects in Project

Hi Sabine,

Thank you for your question.

We are currently in the process of looking at your question.

One of our trainers will contact you on Monday.

Regards

Simon

RE: Levelling resources across projects in Project

Hi Sabine,

Thank you for your question.

The levelling process works exactly the same as if you were levelling for one project. If you use the Standard method it uses the following criteria to determine which task to delay first:

1. Predecessor relationships
2. Slack
3. Dates
4. Priority
5. Constraints

However, you can set a priority level for each project and task to determine which project and task to delay first.

The lower the priority number means the project or task will be delayed first. Then you can grade the others accordingly.

To set a priority for a project or tasks of between 0 and 1000:

Project menu - Project information and set a lower priority number to delay that project first. You can then set individual priorities for each task using the task information box.

So if you had three projects sharing one resource pool A, B and C, if you prefer to delay tasks for Project B first then set a low priority number such as 10.

Alternatively open the resource pool after sharing, choose option 3 and then level the resources.

I hope this answers your question.

Regards

Simon

Tue 4 May 2010: Automatically marked as resolved.


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.07 secs.