Project Start Date
Resolved · Low Priority · Version 2003
Andrew has attended:
Project Advanced course
Project Start Date
How do I adjust the project start date?
RE: Project Start Date
Hi Andrew
Thank you for your question. There are two approaches here and each has a different result.
Using Project > Project information will change the start of the plan. Constraints apply as normal which means that delaying the start of the project will consume like, whilst moving the date earlier in the schedule will likely increase slack.
Alternatively you can turn on the Analysis Toolbar
(View > Toolbars > Analysis) and click Adjust Date.
Using this feature to set the start date moves tasks AND constraints. This means constraint dates change to maintain the amount of slack in the plan.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Kind regards,
Andrew
Tue 27 Apr 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Formatting Bar TextTo display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK. |