microsoft-project-training - milestone

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training - Milestone

microsoft-project-training - Milestone

resolvedResolved · Low Priority · Version Standard

Aisha has attended:
Project Introduction course
Project Introduction course

Milestone

How do I create a milestone??

A

RE: Milestone

Aisha,

Thanks for the question.

To create a Milestone, enter a zero 0 day in the duration part of the task.

Good luck

Regards, Rich


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.09 secs.