microsoft-project-training-courses - how do hide tasks

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training-courses - How do i hide tasks in a schedule

microsoft-project-training-courses - How do i hide tasks in a schedule

resolvedResolved · Low Priority · Version Standard

Vicky has attended:
Project Intro Intermediate course

How do i hide tasks in a schedule

If you have a long schedule but want to show only the key tasks how do you hide the other tasks.

Edited on Thu 29 Mar 2007, 15:33

RE: how do i hide tasks in a schedule

Double click on the task and then in general tab select hide task bar


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.08 secs.