Critical paths
Resolved · Low Priority · Version 2007
Alexandra has attended:
Project Intro Intermediate course
Critical paths
How is the critical path calculated and how can I see it?
RE: Critical paths
Hi Alex
Thank you for your question.
The Critical Path in MS Project identifies those tasks that dictate when your plan will finish. They have no Slack which means if they change (duration, delay) your end date will also change.
You can quickly see the Critical Path by switching to the Tracking Gantt view (View > Tracking Gantt). Critical tasks are highlighted in red.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Tue 29 Dec 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |