Resource shedule
Shared resource schedule and how to see if there is an excess of claim against those resources. Or even that sub projects can see how much labour has been claimed against that pool.
RE: Resource shedule
Hi Ian,
Thank you for your question and welcome to the forum.
I am currently looking at your question and as soon as I have an answer I will email you.
Regards
Simon
RE: Resource shedule
Hi Ian
Thank you for your question - and apologies for the delay in coming back to you. One way to see both assignments across multiple projects and overallocation would be to open the resource pool and look at the resource usage view.
You can add in a column that shows the name of the sub project that contains each task (right click on the label for the task name and choose insert column. From the list select the field called Project).
Overallocation resources will be shown in red and the table will show when overallcation is taking place, across multiple projects.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Wed 9 Dec 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Show or hide toolbar ScreenTipsOn the Tools menu, go to Customize, and then select Toolbars. |