Tasks starting on working days only
Resolved · Urgent Priority · Version 2003
Jeff has attended:
PowerPoint Intermediate Advanced course
Tasks starting on working days only
I have delevoped a generic programme for use on different projects. The commencement date will change depending upon when the project will start. When i change the start date on want to ensure that any task that falls at a weekend starts on the next working day i.e. the following Monday.
How can this be done.
RE: Tasks starting on working days only
Hi Jeff
Thank you for your question. Project does this automatically for you. If the Standard Calendar has weekends as non working days tasks will always be moved to the next available working day.
I hope this helps.
Kind regards,
Andrew
Wed 30 Sep 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |