Forum home » Delegate support and help forum » Microsoft Project Training and help » Critical Path

Critical Path

resolvedResolved · Low Priority · Version 2007

Jill has attended:
Project Introduction course
Project Intermediate course

Critical Path

How do I format to view the critical path?

RE: Critical Path

Hi Jill

Thank you for your question. You can use the Gantt Chart Wizard (from the Format menu or the use the Wand icon on the formatting toolbar). Critical tasks will be highlighted in red.

I hope this helps. Welcome to the forum.

Kind regards,
Andrew


 

MS Project tip: