task lists reports

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Task Lists Reports

Task Lists Reports

resolvedResolved · Urgent Priority · Version 2003

Jeff has attended:
PowerPoint Intermediate Advanced course

Task Lists Reports

How do i produce a report that shows me the tasks lists / task to start on a week by week basis. i.e:

week 1 - tasks 1,2,3,4,5,6 etc
week 2 - tasks 7,8,9
week 3 - tasks 10,11 & 12

etc

RE: Task Lists Reports

Hi Jeff

Thank you for your question. For individual resources you can do this by going to the View menu then choose Reports then select the Assignments group. In that list there will be a report called Todo which generates a list by resource

Alternatively you can export your task information to Excel (File > Save As then choose Excel workbook as your format). Follow the process to export Tasks and on the field mapping step click on Base on Table. From the list select the Entry table and finish the wizard. You can then open the exported Excel file and sort and group in Excel

Kind regards,
Andrew

Wed 16 Sep 2009: Automatically marked as resolved.


 

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips


Server loaded in 0.2 secs.