ms project training london - milestone

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training london - Milestone

ms project training london - Milestone

resolvedResolved · Low Priority · Version Standard

John has attended:
Project Introduction course
Project Intermediate course

Milestone

How do I crate a milestone

RE: Milestone

John

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Rich


 

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips


Server loaded in 0.09 secs.