how do I create a milestone
RE: milestone
Andrew
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Rich
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |