How can I stop resource levelling from splitting course
RE: Project
Hi Dorothy
Thank you for your question. You can stop Project from creating splits in tasks by going to Tools > Level Resources and ticking the box Leveling can create splits in remaining work.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Tue 14 Jul 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |