View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Project Overview - Project Summary Report | MS-Project forum
Project Overview - Project Summary Report | MS-Project forum
Resolved · Urgent Priority · Version 2003
Sarah has attended:
Project Management - Framework & Processes course
Project Overview - Project Summary Report
Problem still unresolved. (see earlier posting today).
I have amended the Resource Sheet to show the unit price per day and it STILL does not give logical answers.
eg ccy 200 per day should give me ccy 400 total for 2 man days. the result I get does not add up.
There must be another constraint that is defined elsewhere. I am using someone else's project plan btw.
PLEASE HELP!
RE: Project Overview - Project Summary Report
Hi Sarah
Thanks for the update - just out of training and got your message. Take a look at the Resource Usage view. Is your resource red (ie overallocated?) or are their hours on certain days edited so that there are more or less than the default 8 per day?
Have fixed costs been added to tasks? (insert the Fixed Cost column)
One way to trouble shoot the plan might be to change the day rate down to
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Enter a DateYou can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you. |