Milestones
Resolved · Low Priority · Version 2007
Cath has attended:
Project Intro Intermediate course
Milestones
how do I move milestone dates on gantt chart?
RE: milestones
Hi Cath,
Thank you for your question and welcome to the forum.
You can hover over the Milestone marker and drag it to a date in the future. Project will add a Start no earlier than constraint.
However, it is unlikely you would do this. Milestone tasks are usually linked to a predecessor task which means that if the predecessor task changes the milestone date would automtically update.
I hope this answers your question.
Regards
Simon
Thu 2 Jul 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |