How do I generate my overall cost for a project?
RE: Costs
Hi Patrick,
Thank you for your question.
There are many answers to this question.
If you add the Project summary task to the Project and then change the table applied to the Gannt Chart to the Cost Table.
Now you will see the Total Cost field and the total cost for the Project Summary task.
Another way of achieving this is to go to the Project menu, Project Information and then Statistics.
I hope this answers your question.
Regards
Simon
Thu 2 Jul 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |