costs

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Costs

Costs

resolvedResolved · Low Priority · Version 2007

Patrick has attended:
Project Intro Intermediate course

Costs

How do I generate my overall cost for a project?

RE: Costs

Hi Patrick,

Thank you for your question.

There are many answers to this question.

If you add the Project summary task to the Project and then change the table applied to the Gannt Chart to the Cost Table.

Now you will see the Total Cost field and the total cost for the Project Summary task.

Another way of achieving this is to go to the Project menu, Project Information and then Statistics.

I hope this answers your question.

Regards

Simon

Thu 2 Jul 2009: Automatically marked as resolved.


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.07 secs.