Splitting Task Start and Stops
Resolved · Medium Priority · Version 2003
Marci has attended:
Project Advanced course
Splitting Task Start and Stops
How to show when work on a task is paused for a period to be resumed at a later date.
RE: Splitting Task Start and Stops
Hi Marci
Thank you for your question. You may wish to create a Summary Task to describe the activity and indent the steps involved in delivering the outcome below it. You might also like to add milestones to mark the start and end of the sequence ot tasks. Now you can adjust the underlying tasks and the Summary task will calculate the overall duration.
Alternatively you may wish to create one task and use split (Edit > Split) to break the task into smaller but connected pieces.
Kind regards,
Andrew
RE: Splitting Task Start and Stops
Hi Marci,
Thank you for your question.
There are two methods to show that the remaining portion of a task needs to rescheduled for a date in the future:
1. Split the task to the desired date.
2. Use the Update Project option which is available via the Tools menu and Tracking.
I hope this answers your question.
Regards
Simon
Wed 1 Jul 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |