Forum home » Delegate support and help forum » Microsoft Project Training and help » course ms project - Milestone

course ms project - Milestone

resolvedResolved · Low Priority · Version Standard

Carole has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Milestone

How do I create the above?

RE: Milestone

Carole

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips