To create a custom filter, navigate to the project menu and then Filtered For. Select the More Filters option and then click the New button.
Then you can name the new filter and set the lines of criteria you need.
I hope this answers your question.
Regards
Simon
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |