How do you allocate tasks to different people/ job types
RE: Resource
Hi Karen
In MS Project the resource is assigned to the task, rather than the other way around.
One of the ways to do this is to split the screen (Window > Split) then click on a task. In the lower left pane of the split click below the column Resource Name then choose your resource from the list and click OK.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Mon 15 Jun 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |