Forum home » Delegate support and help forum » Microsoft Project Training and help » Priority rating for tasks

Priority rating for tasks

resolvedResolved · Low Priority · Version 2003

Chris has attended:
Project Intro Intermediate course

Priority rating for tasks

just a quick clarification please: when using the priority setting for each task was it that if you set a task with a priority of 1000 then the leveling function would not automatically change the resourcing for this task? Thanks.

RE: priority rating for tasks

Hi Chris,

Thank you for your question.

If you assign a priority level of 1000 to a task, if you then use Resource Levelling to resolve all the Resource overallocations, it will skip that task allowing you to resolve it yourself.

I hope this has answered your question.

Regards

Simon

RE: priority rating for tasks

Simon - many thanks for your response on and clarification. Just one further thing - did you say during the course that the files we produced and worked on during the course would be made available agaisnt our account and could be downloaded? Need to jog my memory a little !! :)

Thanks,

Regards
Chris

RE: priority rating for tasks

Hi Chris,

Thank you for your post.

The files we worked on won't be available in your delegate account. The files included in the zipped folder are the project files needed to complete the review exercises in your full manual.

Please find attached a copy of the shed project we completed.

I hope this helps.

Have a great weekend.

Regards

Simon

RE: priority rating for tasks

Hi Chris,

Further to my previous email, I cannot send the project file through this forum Post reply.

If you would like a copy of the Shed Project we did, could you please reply to this email and give me the email address you would like me to send the file to.

Have a good weekend.

Regards

Simon

RE: priority rating for tasks

Thanks for your very prompt response Simon.

Sorry I must have misheard about the working files we created. My mail address for the shed project is chris.haygarth@ntlworld.com.

Many thanks. .

Regards
Chris

Wed 27 May 2009: Automatically marked as resolved.


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)