can I create my on fields?

RE: fields

Hi Helen,

Thank you for your question.

You can create your own fileds showing additional information or custom calculations based on existing project fields.

Go to Tools, Customize and then Fields.

I hope this answers your question.

Regards

Simon

Tue 19 May 2009: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips