Work level available
Resolved · Low Priority · Version 2007
Ben has attended:
Project Intro Intermediate course
Work level available
when looking to level work is there a way of viewing the max level of 'work' available for allocation so that you can see the variance for levelling?
RE: Work level available
Hi Ben,
Thank you for your question.
If you change the view to Resource Usage and right click over the hours window, choose the Remaining Availabilty and it should add it as a row.
I hope this answers your question.
Regards
Simon
Tue 12 May 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Project Communityin the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips. |