Critical Paths
Resolved · Medium Priority · Version 2003
Mark has attended:
Project Introduction course
Critical Paths
How do I set a critical path?
Can it be confirmed that this is for identifying potential weakness in my project timings?
RE: Critical Paths
Hi Mark
Thank you for your question. MS Project calculates the critical path for you automatically. In essence it highlights those tasks that determine when your Project will finish that have no float. This means that if you delay critical tasks you wll also delay your project. Whilst there is nothing wrong with tasks that are critical if your entire plan is critical then any change at any point will impact when the plan finishes.
A quick way to see the critical path is to switch to the Tracking Gantt view (View > Tracking Gantt)
I hope this helps. Do let us know if you have any further questions.
Kind regards,
Andrew
Thu 16 Apr 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |