SS, SF, FF
Resolved · Low Priority · Version 2007
RE: SS, SF, FF
Hi John
Thank you for your question
I assume you are referring to different dependency types Start to Start, Start to Finish etc
Create your task dependency in the normal way and then double click on the arrow head of the link. This will open the task dependency properties dialog, and you can select the required type there
Regards
Stephen
Thu 16 Apr 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |