MS Project Security

resolvedResolved · Low Priority · Version 2003

Iaan has attended:
No courses

MS Project Security

Is it possible to have different levels of security within your Resource Pool Sheet, i.e. a level for managers and a level for admin staff?

RE: MS Project Security

Hi Iaan

Thank you for your question. Within MS Project there are no levels of security. To implement security roles you would need to introduce Microsoft Project Server. You can find more details here:

http://office.microsoft.com/en-us/projectserver/FX100739841033.aspx

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Tue 14 Apr 2009: Automatically marked as resolved.


 