Schedule
Resolved · Medium Priority · Version 2007
Narain has attended:
Project Introduction course
Schedule
Could you plz send me some more information on the 'Update as scheduled' button ?
Thanks
Narain
RE: Schedule
Hi Narain,
Thank you for your question.
The Update as Scheduled button changes the actual dates of all or selected tasks to match the schedule. So this button is only used if you are sure the tasks were all completed as per the schedule.
If some of the tasks have started or finished later than scheduled, then you need to use the Update Tasks button on the Tracking toolbar.
I hope this answers your question.
Regards
Simon
Thu 9 Apr 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |