microsoft-project-training-courses - how do you deal

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training-courses - How do you deal with circular activities? | MS-Project forum

microsoft-project-training-courses - How do you deal with circular activities? | MS-Project forum

resolvedResolved · Low Priority · Version Standard

Jim has attended:
Project Intro Intermediate course

How do you deal with circular activities?

Where a task has two outcomes, one of which is a feedback loop to re-do the task?

RE: How do you deal with circular activities?

LIKE EXCEL THIS SHOULD TELL YOU YOUR TASK ACTIVITIES HAS BEEN SET UP WRONG


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.