Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Tracy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |