duration changes decimal figures

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Duration Changes to Decimal figures

Duration Changes to Decimal figures

resolvedResolved · Medium Priority · Version 2003

Mark has attended:
No courses

Duration Changes to Decimal figures

Hi,

I've started a new Project and adjusted the Work timings, after adding several tasks the duration figure is full days. However, when I have a task with 3 or more resources attached and then add a constraint on the task of Must Start On or Start No Earlier this changes the duration time to decimal places. ie) 2 days to 2.57. Is there anyway to stop this occuring?

RE: Duration Changes to Decimal figures

If you want Durations to stay "in place" as best as they possibly can, then you should leverage "Fixed Duration" and "Not Effort Driven".

1. Change your default options so that any new tasks are set this way:
Click on >Tools, >Options, >Schedule Tab
Select "Fixed Duration" for the Default task type.
Uncheck the option New tasks are effort driven

2. Change these options for existing tasks
Insert the column Type. Change all to Fixed Duration.
Insert the column Effort Driven. Change all to No.

Now Durations should hold when you add resources or establish constraints. (use caution in these constraints. You are eliminating the dynamic scheduling capabilities of Microsoft Project).

Hope this helps!
J Black
http://www.pmconnection.com


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.07 secs.