Resolved · Low Priority · Version 2003
Debbie has attended:
Project Introduction course
Resources
How do you show initials rather than full name beside the bars on the GANTT chart
RE: Resources
Hi Debbie
Thank you for your question. To put the initials beside the bars on the Gantt chart try this: From the format menu choose Bar styles. The dialogue box that appears shows the objects that can be formatted with the Task type already selected as it's first in the list. At the bottom of the dialogue box switch from the bar tab to the Text tab. You will see that there are several slots around a bar that can hold data from the database. One is already used (Right) which contains the Resource name field. Click on Resource name and replace it with the Resource initials field. OK out of the dialogue box and take a look at the Chart. You should find the initials of any assigned resources appear beside the bars rather than the full names.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Mon 2 Mar 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Enter a DateYou can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you. |