RE: Microsoft Project
Hi Sandy
Thanks for your question.
Tasks are calculated by project as critical if they determine the end date of your project and have no slack (float). This means it's not something that we set in the software rather it's calculated for us by Project.
I hope this helps - do let us know if you have any other questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |