98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Project Tasks reflectin real life
Project Tasks reflectin real life
Resolved · Urgent Priority · Version 2003
Project Tasks reflectin real life
I am relatively new to Microsoft Project so this is probably a stupid question but here goes:
I have read and understand the three factors involved in the Project calculations. My frustration is that in real life a person will work 80 hours in a two week period and they may accomplish several tasks in that time but they are not necessarily back to back. Maybe I start a task today that is going to take 6 hours but it can't be completed because I'm waiting on information. I get that information ten days later and finish the task. How can I log the task in Project so that what happened in real life is reflected? As long as the tasks I've completed over the two weeks add up to 80 hours I should be able to reflect what happened .... right?
I'm making this an urgent question because I have to turn in the project for review and I can't seem to figure out how to do this.
RE: Project Tasks reflecting real life
Hi David
Thanks for your question. To summarise you have a plan with tasks that also have assigned resources. You have probably also saved a Baseline (Tools > Tracking > Save baseline) so that you can compare your progress with the originally agreed schedule.
When it comes to recording what really happens you have a couple of choices.
Simplest is to double click on a task and record the percentage complete. In its simplicity though it loses detail. It wouldn't really help in the example you quote for instance as it's not precise enough and it is designed to measure duration complete rather than work.
An alternative might be to switch views and have a look at the Resource Usage view.
This view re-organises your project and groups your tasks by the resource assigned to do them. So in this example you would find the resource in question and under their name find the task to update.
On the right hand side of the screen you will seen the sheet (called Time phased data) that shows when planned work will take place. You now want to add what actually happened. To do this right click anywhere in the yellow sheet on the right and select Actual data form the menu that appears.
Now you can type below the planned work for each day what was actually completed. If you record less hours than planned Project will extend the duration of the task to carry the unfinished work forward.
If you anticipate work will start but there will be a gap of a few days before work resumes put zero on the gap days and Project pushes the unfinished work amounts later in the schedule.
If you switch back to the Gantt view you will find the task bar has some progress recorded and split (dotted blue line reflecting the zero days) with the unfinished work completing the bar later in the schedule.
Try experimenting with this using one task and one resource and see if it models the results you are looking to achieve.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Thu 19 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |