98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Effort driven scheduling
Effort driven scheduling
Resolved · Low Priority · Version 2007
Paul has attended:
Project Introduction course
Effort driven scheduling
How would I know when to use effort driven scheduling? HOw would I know what default to set on my copy of project.
RE: Effort driven scheduling
Hi Paul
Thanks for your question. The best way of working out whether to use effort driven scheduling or not is to consider whether or not most of the activities you are planning change duration if you add or remove resources from them.
By default Effort Driven Scheduling is on for all your tasks. To switch this off for new tasks go to Tools > Options > Schedule and remove the tick from New tasks are effort driven
Click on OK to apply this change to new tasks in your current project or click on Set as Default to apply this change to all new projects created with your installation of Project
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Thu 19 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |