View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Project start up
Project start up
Resolved · Low Priority · Version 2003
Richard has attended:
Project Intro Intermediate course
Project start up
how do you enter a project start date
RE: project start up
Hi Richard
Thanks for your question - you can set the project start date by going to the Project menu and choosing Project Information. From here you can set your estimated start date.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Mon 16 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |