98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Adding a milestone
Adding a milestone
Resolved · Low Priority · Version 2003
Jennifer has attended:
Excel Advanced course
Project Intro Intermediate course
Adding a milestone
How do I add a milestone?
RE: Adding a milestone
Hi Jennifer
Thanks for your question - to add a milestone create a task and set its duration to zero. The task on the chart becomes a diamond symbol with a date attached.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Set default task type - Project 2010a. In Project, click on the File tab |