Forum home » Delegate support and help forum » Microsoft Project Training and help » Project

Project

resolvedResolved · Low Priority · Version 2003

Andy has attended:
Project Introduction course
Project Intermediate course

Project

How do you link projects and what was the best thing before last bread?

RE: Project

Hi Andy

Thanks for your questions. One way to join projects together is to open a new blank project then from the insert menu insert each project to be linked. Use the mouse to drag relationships between the tasks you want to join together across the projects. You can now close and save your files. A link will have been created between the projects. You don't need to keep the combined file for the link to remain.

With regard to the best thing before sliced bread I'd suggest the bread knife!

Thanks for joining the forum - let us know if you have any more questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.