Project
Resolved · Low Priority · Version 2003
RE: Project
Hi Wendy
Lag represents a delay between the successor and its predecessor, usually in working days. You can add Lag by double clicking on an arrow between two tasks or by clicking on a successor task in the task list and going to the predecessor tab.
I hope this helps - please let us know if you have any further questions.
Kind regards,
Andrew
Tue 3 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Use Autofill in MS Projecta. Complete 1st entry |