How do I integrate other people's project plans into an overall Programme plan written in Project?

RE: MSProject

Hi Veronica

A quick way to do this is to create a new blank project and from the insert menu choose Project... from here you can browse through to find a file to add to your consolidated project. Repeat to add more projects.

I hope this is helpful - let us know if you have any further questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Server loaded in 0.08 secs.