Critical path
Resolved · Low Priority · Version 2003
Christopher has attended:
Excel Introduction course
Critical path
in the Gant chart, what is the significance of the red lines?
RE: Critical path
Hi Christopher
Thank you for your question. On the Tracking Gantt view you can see tasks that are red and blue. Red tasks are critical tasks (that is they influence the end date and have no slack or float around them).
I hope this helps - please let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |