Resource Sharing
Resolved · Low Priority · Version 2003
RE: Resource Sharing
Hi Ekow
Thank you for your post to the forum. Resource sharing is a means to having a single pool of resources shared between several projects. A resource pool is a project plan with only the resource sheet completed. To connect a plan to the resource pool first open resource pool the open the project plan that needs resources. In the project plan go to the tools menu and choose resource sharing then click on share resources and set the plan to use resurces from the pool.
I hope this helps - do let us know if you have any questions.
Kind regards,
Andrew
Mon 9 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |