RE: project
Hi Ravinder,
Thank you for your question.
If you want to create a custom filter then follow these instructions:
1. Access the Project menu followed by 'Filtered for'
2. Select 'More Filters'
3. Select 'New'
4. Now enter the criteria
I hope this answers your question.
Regards
Simon
Mon 26 Jan 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |