course ms project - Resource cost

resolvedResolved · Low Priority · Version Standard

Ben has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Resource cost

How do i change the resource cost from a daily rate to an hourly?

RE: resource cost

Ben

In the resource sheet, under standard rate, enter 100/d for


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.