Critical Path

What is a critical path and how do I view it?

RE: Critical Path

Hi Joanne

You can always refer to your course reference material or online help for the definitve on critical path. To summarise; the crtical path denotes linked tasks in your project plan with minimum or no slack (float).
In Project you have the option to set exactly how much float sets a task as "critical". There are several ways to view your critical path, one way is to goto Project menu, then "Filtered for: all tasks", then "Critical"

Hope this helps

Regards

Jacob


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips