Tracking costs and resources

resolvedResolved · Low Priority · Version 2007

Adeeba has attended:
Project Intro Intermediate course

Tracking costs and resources

how do you track resources time when 2 or more resources are working on the same task but they will not be spending the same amount of time on the task?

RE: tracking costs and resources

Hi Adeeba

thank you for your question. You may find it easier to work in the Task Usage view (View > Resource Usage). This view shows the project organised by Task and then lists all the resources assigned to that task. By right click on the time phased information to the right you can add an actual row for each assignment. This allows you to track actual work by resource for each task.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Mon 29 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.09 secs.