Tracking costs and resources
Resolved · Low Priority · Version 2007
Adeeba has attended:
Project Intro Intermediate course
Tracking costs and resources
how do you track resources time when 2 or more resources are working on the same task but they will not be spending the same amount of time on the task?
RE: tracking costs and resources
Hi Adeeba
thank you for your question. You may find it easier to work in the Task Usage view (View > Resource Usage). This view shows the project organised by Task and then lists all the resources assigned to that task. By right click on the time phased information to the right you can add an actual row for each assignment. This allows you to track actual work by resource for each task.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Mon 29 Dec 2008: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |