Is it possible to rename the Flag1 column?

RE: MS Project 2007

Hi Laurence

The Flag column can re renamed as follows:
From the Tools menu choose customise > fields
In the dialog box change the field type to Flag. Select Flag1 and click rename. Once you have applied the name you will be able to find the field listed both under its original and new name in field chooser lists.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 29 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips