Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project

MS Project

resolvedResolved · Low Priority · Version 2007

Carole has attended:
Project Intro Intermediate course

MS Project

How do you link projects together?

RE: MS Project

Hi Carole

Thanks for your question. Projects can be linked in a number of ways. One approach is to create a new blank project then from the insert menu choose to insert a proect and then browse to find the first project you would like to connect.

Choose insert again and choose the second file to connect. In your temporary project you should now see two lines (summary tasks). Clicking on the the minus icon beside each row will display the details of each project. It's possible then to drag and link between individual tasks and join the projects together.

I hope this helps - let us know if you have any further questions.


Kind regards,
Andrew

Mon 29 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes