RE: MS Project
Hi Carole
Thanks for your question. Projects can be linked in a number of ways. One approach is to create a new blank project then from the insert menu choose to insert a proect and then browse to find the first project you would like to connect.
Choose insert again and choose the second file to connect. In your temporary project you should now see two lines (summary tasks). Clicking on the the minus icon beside each row will display the details of each project. It's possible then to drag and link between individual tasks and join the projects together.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Mon 29 Dec 2008: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Create own ribbon tab - Project 2010a. In Project click on the File tab |