How do you change one task/resource so that you can set muultiple calendars to it. ie. the task runs mon to fri (@

RE: PROJECT

Hi Kelly,

Thank you for your question.

After speaking to my colleagues, set the resource calendar to work on that saturday.

Then go to resource sheet and double click on the resource in question. Go to the Costs tab and set an effective date in the second row for the saturday in question and put the rate of 60 per hour in Cost Rate table A.

Then you need to set the original 50 per hour back by typing in sundays date(next day) in the third row, which means any work assigned will switch back to the original rate.

I hope this answers your question.

Regards

Simon

Mon 19 Jan 2009: Automatically marked as resolved.


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Server loaded in 0.1 secs.