Can you show a full view of the gantt chart for a project covering 3 years with only one years activities highlighted?
RE: MS Project
Hi Penny
One way to achieve this is to could be to apply a date range filter. From the Project menu choose Project > Filtered for > Date Range. Specify the beginning of the range of dates followed by the end of the range. Project will filter the view to show only those tasks that meet your criteria.
Lastly you may wish to zoom your project to show all the bars on one screen. From the View menu choose Zoom then select Entire Project.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Mon 29 Dec 2008: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |