How do I change the project start date?

RE: MS Project

Hi Ida

Thanks for your question. You can specify the estimated start date for your project by going to the Project menu and choosing Project Information.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 8 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.